Before executing a ground lease or build-to-suit lease, tenants—especially institutional or industrial users—typically require certain core infrastructure improvements to be completed by the landowner or developer. These improvements ensure the site is physically and operationally ready for occupation, construction, or regulatory approvals. They are often listed as preconditions to lease execution or rent commencement.
Below are the essential utility and access upgrades that must be delivered before lease finalization:
1. All-Weather Road Access to the Parcel
- Requirement:
- Internal approach road (minimum 9–12 meters wide) must be laid or graded with a compacted sub-base or bitumen surface.
- Safe and direct connection to public road or industrial park spine road.
- Internal approach road (minimum 9–12 meters wide) must be laid or graded with a compacted sub-base or bitumen surface.
- Purpose:
- Enables movement of construction equipment, heavy vehicles, and utilities.
2. Electrical Power Connection (HT/LT)
- Requirement:
- Dedicated power connection approval from the state utility (e.g., TANGEDCO, MSEB).
- Transformer or feeder installation readiness based on the tenant load requirement.
- Provision of HT/LT panel room, metering infrastructure, and distribution cabling pathways.
- Dedicated power connection approval from the state utility (e.g., TANGEDCO, MSEB).
- Purpose:
- Required for construction, safety systems, and industrial licensing.
3. Water Supply Infrastructure
- Requirement:
- Connection to municipal supply or on-site borewell with overhead tank/sump.
- Minimum service pressure and availability confirmation.
- Pipeline laid up to the tenant plot boundary with control valves.
- Connection to municipal supply or on-site borewell with overhead tank/sump.
- Purpose:
- Required for site preparation, sanitation, and operations.
4. Drainage and Stormwater Management
- Requirement:
- Open or underground stormwater drains along internal roads.
- Slope grading and outfall connectivity to public drains or recharge pits.
- Open or underground stormwater drains along internal roads.
- Purpose:
- Prevents flooding and erosion during the development phase.
5. Sewage or Effluent Provisions
- Requirement:
- Provision for connection to park-level STP/CETP, or outline of temporary disposal mechanism.
- Manhole chambers or stub points near the plot boundary.
- Provision for connection to park-level STP/CETP, or outline of temporary disposal mechanism.
- Purpose:
- Required for environmental clearance and worker facility approval.
- Required for environmental clearance and worker facility approval.